Key takeaways
- WIP is cost awaiting transfer day. It is neither an expense nor profit, and it is presented as inventory under TAS 2
- During construction, revenue and COGS are zero, but overhead and marketing costs go through the P&L, so accumulated losses are normal
- Overstated WIP defers tax that will come back as a liability. Understated WIP means paying more tax than necessary
- Check construction-cost WIP against BOQ progress every quarter, and keep supporting documents for every entry
In property development businesses, whether single-detached houses, townhouses, condominiums or villas, the most significant and most misunderstood accounting item is Work In Progress (WIP). WIP is not an expense; it is an asset that accumulates costs in the statement of financial position until the ownership transfer day. Understanding this mechanism is therefore central to project management, tax planning and communication with banks, investors and auditors.
What WIP is in the financial statements
WIP is an asset account that collects the costs incurred while developing a project: construction costs under the BOQ, design fees, project consultancy fees, interest during construction (IDC) and land costs. Projects held for sale are classified as inventory under TAS 2 and are generally presented as current assets according to the operating cycle, even though it may take several years to sell out.
During construction, WIP is usually the largest asset item. It reflects the capital tied up in the project, which is normal for a developer.
The most important consequence is that WIP does not affect the income statement during construction. Every baht paid as a project cost sits in WIP and comes out as cost of sales when revenue is recognised under TFRS 15 at the point control is transferred to the customer.
Effects on the financial statements across the 3 stages of a project
Stage 1: During construction
The project does not yet recognise revenue under TFRS 15 because ownership has not been transferred, so revenue and COGS are zero. However, office overhead, such as office staff salaries, travel and general administration, and marketing costs must be expensed immediately. Commission that is an incremental cost of obtaining a contract is recorded as a contract cost asset, separate from WIP. The company therefore shows accumulated losses in this stage.
In the statement of financial position, WIP keeps rising, borrowings peak as construction nears completion, and equity often falls or turns negative because of accumulated losses. This looks worrying to outsiders but is normal, because all of the profit is recognised during the transfer period.
Stage 2: The year of ownership transfer
On the transfer day of each unit, the WIP for that unit moves into COGS as the full amount of revenue is recognised. A year with many transfers therefore shows unusually high revenue and gross profit compared with the previous year.
WIP falls in line with the number of units transferred. Cash increases from customers and from escrow withdrawals, while tax payable rises, both Specific Business Tax (SBT) and corporate income tax (CIT).
Stage 3: After all units have been transferred
WIP is zero and no further revenue arises. The project is considered closed in accounting terms. The owner must decide whether to wind up the company or keep the legal entity for the next project, which has a significant effect on tax and on the cost of starting a new project.
6 principles for planning WIP correctly
Principle 1: Clearly separate WIP from expenses
Record in WIP (capitalise)
- Construction costs under the BOQ, in every category
- Design and architect fees
- Project management fees directly related to construction
- Interest during construction that meets the conditions of TAS 23
- Land costs and land tax during development
- Show unit costs, only for work that remains as part of the units to be sold
Do not capitalise in WIP
- Office overhead
- Marketing and advertising costs
- Commission (recorded separately as a contract cost asset, or as an expense, under TFRS 15)
- Specific Business Tax and transfer fees at the time of sale
- Interest on overdrafts or working capital not directly related to construction
Principle 2: Calculate WIP per square metre correctly
WIP per square metre is a key indicator for estimating the COGS of each unit sold. It is calculated as total project cost divided by the project's total net saleable area (NSA). This figure should be updated every year, particularly when a cost overrun occurs, when the BOQ is revised, or when phases are added or removed.
Principle 3: Beware of overstated WIP
Overstated WIP results from capitalising items that should be expenses. This inflates COGS on the transfer day, understates profit and makes the tax for the transfer year lower than it should be. Although this may look like a short-term benefit, the Revenue Department may issue a retrospective assessment with penalties and surcharges, and the auditor may raise observations, up to issuing a qualified opinion.
Principle 4: Beware of understated WIP
If WIP is understated, COGS in the transfer year will be low, gross margin will look better than it really is, tax will be higher than it should be, and banks or investors may misjudge the project's position, leading to wrong strategic decisions.
Principle 5: WIP must be consistent with actual progress of the work
Construction-cost WIP in the accounts must be consistent with the BOQ progress report.
Expected construction-cost WIP = BOQ progress (%) × construction budget
Example: Construction is 45% complete at year-end and the construction budget is THB 2,400 million. Expected construction-cost WIP is THB 1,080 million. If the accounts show THB 1,650 million, that is THB 570 million higher than it should be. You must check immediately whether any items have been wrongly capitalised or whether advance payments are mixed in.
Compare only the construction-cost sub-ledger with the construction budget. Do not compare total WIP, which includes land and IDC, with BOQ progress, because the result will be distorted straight away.
Principle 6: A document trail for every entry
Every item recorded in WIP must have a purchase order (PO), the contractor's invoice, a progress report from the project manager or quantity surveyor, and approval documents from an authorised person. These documents let you answer the auditor's questions on every baht, guard against queries from the Revenue Department, and serve as evidence if a retrospective tax assessment is made.
The golden rule of WIP management
WIP is cost awaiting transfer day. Setting WIP too high defers tax that will come back as a burden later. Setting it too low means paying more tax than necessary. Setting it correctly means matching actual costs with actual revenue.
Project executives should review WIP every quarter against BOQ progress and work closely with the accounting team, the project team and the auditor, so that the figures in the financial statements reflect the true position. This is the basis for business decisions and for credibility with all parties.