01 · Key DecisionsDecisions to make
- Whether to approve a variation order Every VO affects Cost-to-Complete and contingency
- How to use contingency Who approves it, and what remaining balance triggers a report to the board
- Whether to adjust the sales plan Price, promotions and payment terms when absorption is below plan
- When to call for additional capital This should be known in advance, not when cash is nearly gone
- Whether to accelerate the work or accept delay Compare acceleration costs with interest and the effect on the transfer day
02 · Finance · Tax · LegalFinance, tax and legal tasks
Finance
- Pay the contractor against progress payment certificates (IPC) certified by the QS, and record retention in the register
- Draw down funding against the S-curve and track IDC monthly
- Prepare a cost-value reconciliation and Cost-to-Complete monthly
- Forecast cash flow on a 13-week basis and over the life of the project
- Report Covenants and progress to funders on schedule
Accounting and tax
- Accumulate development costs as inventory under TAS 2 and test net realisable value (NRV) when market prices or costs change
- Withhold 3% WHT on contract work and services, and file PND 3 or PND 53 depending on the recipient
- Manage input VAT and file PP 30 monthly. A project selling condominium units pays SBT, not VAT, so eligibility for input VAT credit must be checked with the auditor or tax adviser
- The current VAT rate of 7% applies until 30 September 2027 under the latest Royal Decree
- File PND 51 within 2 months after the end of the first half of the accounting period, and PND 50 within 150 days after the end of the accounting period
- Customer instalments remain a contractual liability throughout construction
Law
- Build in line with the conditions of the EIA report and the building permit; design changes that affect those conditions must be checked before the work is done
- Keep a monthly foreign quota register so that it matches the figures the condominium juristic person will manage later
- Check that the bond and the CAR policy remain valid and still provide cover if the programme slips
03 · RoadmapRoadmap tasks
P7 Construction, cost control and financing during construction
| # | Task | Category | Responsible party | Outcome | Time |
|---|---|---|---|---|---|
| 7.2 | Inspect progress payments & certify monthly | Investment budget | QS/PM | Certified IPCs, valuation, retention | Monthly |
| 7.3 | Draw down funding per the S-curve | Finance | Finance team | Drawdowns against plan, track IDC | Monthly |
| 7.4 | WHT on contractor/consultant fees | Finance | Finance team | Withhold WHT & file returns | Monthly |
| 7.5 | Manage input VAT | Finance | Finance team | Record/reclaim input VAT | Monthly |
| 7.6 | Remaining cost & budget vs actual (CVR) | Investment budget | QS/Finance | Monthly cost-value reconciliation report ⚠ Track cost overruns early | Monthly |
| 7.7 | Variations / change management | Legal/CAPEX | PM | VO register, contingency usage control | Ongoing |
| 7.8 | Monitor quality, safety & environment | Law | PM | Inspection reports, safety & monitoring | Ongoing |
| 7.9 | Track sales & foreign quota register | Legal/finance | Sales/Lawyer | Sales vs plan, foreign quota register | Monthly |
| 7.10 | Collect buyer instalments (contract liability) | Finance | Finance team | Collect instalments; record as revenue received in advance | Per instalment |
| 7.11 | Comply with funding conditions & report to funders | Finance | Finance team | Report conditions/financials to funders | Quarterly |
| 7.12 | File corporate income tax returns per cycle | Finance | Tax team | Half-year & annual tax returns | Per cycle |
| 7.13 | ◆ Structure topped out | Technical | Contractor | Structural completion milestone | Milestone |
04 · MetricsMetrics to watch
| Figure | Reference level from the source document | Notes |
|---|---|---|
| Cost-to-Complete vs budget | Within budget + 5–10% contingency | Thai industry overruns budgets by 5–15% on average, per Chapter 1 |
| Remaining contingency vs remaining work | Should reduce in proportion to the work done | Using it faster than progress is a warning sign |
| Actual vs S-Curve | Per baseline programme | Look at both actual work and funds drawn |
| Presale before construction completion | Target 60–80% | Used to plan refinancing and the transfer day |
| Overdue instalments | Track AR aging | A sign that customers are abandoning their down payments |
| DSCR, LTC, Sales-to-Drawdown | Per Covenant; reference DSCR 1.25x–1.50x | Forecast headroom in advance, at least quarterly |
| Cash runway to transfer day | Must not go negative in the stress case | The most important figure at this stage |
Estimate at Completion = cumulative actual cost + Cost-to-Complete
Cost overrun = Estimate at Completion - approved budget
05 · Decision GateDecision gate
The main gate at this stage is topping-out, plus monthly gates from the cost and cash reports. The choice at this stage is usually not whether to stop the project, but how to close the gap as quickly as possible
Proceed as planned
- Estimate at Completion is within the total budget including contingency
- Actual work is not behind the S-curve by more than the agreed threshold
- Sales and instalments are on plan
- Covenants have headroom
- Cash is sufficient to reach transfer day in the stress case
Pause to adjust the plan
- Forecast cost exceeds contingency: do VE, negotiate VOs, raise additional funding
- Presale below plan: adjust prices and terms, and retest Peak
- Contractor in financial difficulty: check the bond and the fallback plan
- Close to breaching a Covenant: talk to the funder before the reporting date
06 · Common PitfallsCommon pitfalls
- Reporting only the construction percentage and not Cost-to-Complete
- Approving VOs one by one without looking at the aggregate effect on contingency
- Paying progress payments on the contractor's request without independent certification
- Failing to stop capitalising interest in time when development is mostly complete, or continuing to capitalise during long work stoppages
- Waiting until a Covenant breach is close before informing the funder
- Not adjusting the transfer day in the model when work is delayed
- Letting FF&E and fit-out costs at the end of the project exceed budget because attention was only on structural work