Chirayuthchai TraisaengsatheanStrategic Finance for Property Development

Accounting for VAT refunds from the Revenue Department

The accounting cycle from input VAT to receipt of the refund, partial approvals, and the limits on input VAT for businesses selling real estate

Key takeaways

  • A VAT refund is not revenue. It is the settlement of a receivable from the Revenue Department and does not affect WIP
  • Before recognising a receivable, check whether the input VAT is creditable
  • Input VAT on constructing buildings for sale, where the sale is subject to Specific Business Tax (SBT), may be prohibited input VAT and become a project cost
  • The VAT receivable must always be presented separately from WIP

Introduction

In large construction projects, developers often pay a large amount of input VAT to contractors before any output VAT arises. If the business is entitled to claim input VAT credit, this accumulated balance can be refunded by the Revenue Department. Accountants are often unsure how to record the refund once received and whether it affects project cost. This article explains the accounting for the whole cycle.

Check first: The cycle in this article applies when input VAT is creditable, for example for a business that is subject to VAT. Sales of real estate fall under SBT, and Supreme Court Judgment No. 2549/2732 held that input VAT on constructing buildings whose ownership is transferred and which are subject to SBT is input VAT that may not be deducted under Section 82/5(6). In such a case the VAT is not a receivable and should be considered for inclusion in WIP cost. Projects that have both a sale portion and a portion subject to VAT must apportion input VAT with a tax adviser.

The full accounting flow

This example uses a VAT rate of 7%, which is a reduced rate below the statutory rate; the latest royal decree is reported to extend it to 30 September 2027. Check the current rate before use.

Step 1: Receive the contractor's invoice

Dr. WIP – construction cost 1,000,000

Dr. Input VAT 70,000

Cr. Contractor payable 1,070,000

Step 2: Pay the contractor

Dr. Contractor payable 1,070,000

Cr. Cash/bank 1,070,000

Step 3: File PP 30 to claim the refund

When input VAT exceeds output VAT, the business may choose to claim a cash refund instead of carrying the balance forward as a credit against the following month, by transferring the balance to a receivable from the Revenue Department.

Dr. VAT refund receivable 70,000

Cr. Input VAT 70,000

Step 4: Receive the refund

Dr. Cash/bank 70,000

Cr. VAT receivable 70,000

Receiving the refund at this step has no effect on the WIP account. It is simply the settlement of a debt owed by the Revenue Department.

The full cycle of a VAT refund

StepsInput VATVAT receivableCash
Receive invoice70,00000
Pay contractor (including VAT)70,0000(1,070,000)
File PP 30070,000(1,070,000)
Receive refund00(1,000,000)

At the end of the cycle, the net cash outflow equals the WIP of THB 1,000,000, as it should.

Presentation in the statement of financial position

ItemTHBClassification
WIP – construction cost1,000,000Inventory
VAT receivable70,000Current assets

The VAT receivable must always be presented separately from WIP because it is a claim against the Revenue Department, not part of project cost.

Special cases to watch

1. The Revenue Department approves only part of the refund

If some items are not approved, for example because of incomplete tax invoices or because the input VAT is prohibited, the unapproved portion must be recognised as an expense, or as project cost if it is input VAT related to costs and did not arise from a documentation error. The effect on net taxable profit should also be reviewed.

Dr. Cash/bank (portion received)

Dr. Disallowed tax expense (portion not approved)

Cr. VAT receivable (full amount originally recognised)

2. VAT that cannot be refunded because the deadline has passed

If the refund deadline under the Revenue Code has passed, check the applicable section and the time count with a tax adviser. The VAT receivable must be written off, on the following principles:

  • If the project is still under construction and the item is a directly related cost, consider Dr. WIP / Cr. VAT receivable
  • If the project is complete, or the loss arose from a failure to follow up, consider Dr. Expense / Cr. VAT receivable

3. Interest on delayed refunds

Section 4 Decies of the Revenue Code authorises payment of interest on refunded tax at 1% per month or part of a month, under the criteria set out in a ministerial regulation, so it does not arise in every case of delayed refund. When received, record it separately as income.

Dr. Cash/bank

Cr. Interest income from the Revenue Department

Conclusion

When input VAT is creditable, receiving a VAT refund is simply the clearing of the receivable from the Revenue Department and the return of cash to the business. It is not revenue and does not affect WIP. The points that need the most care are (1) establishing the right to input VAT credit before recognising the receivable, (2) following up the status of the refund claim regularly, and (3) recording adjustments when the Revenue Department approves less than the full amount or when the refund deadline has passed.

Keeping WIP and the VAT receivable clearly separate means the financial statements reflect the project's true position and helps management see correctly the cash flow awaiting refund from the government.