How to build a monthly funding gap analysis

Steps for building a monthly cash table, the core formulas, checkpoints, and options when a funding gap appears

Key takeaways

  • A funding gap is the money needed beyond the equity and facilities arranged. It should be visible months in advance.
  • The table must separate inflows, outflows and sources of funds by month, and check that Sources equal Uses every month.
  • The example project has a Peak Funding of THB 867.9 m, but the funding gap that must be found is THB 49.7 m in month 30, because equity and facilities cover the rest.

What this table answers

A funding gap analysis answers three questions: in which month the shortfall begins, how large the shortfall is at its peak, and when cash flow turns positive again. The monthly table should cover the full project term, while near-term liquidity management should have a separate 13-week forecast.

Steps to build it

  1. Set the time axis. Use months running down the rows and set month 0 as the construction start date. Negative values are the project preparation period.
  2. Enter a single set of assumptions. Keep inputs separate from formulas, including costs, programme, payment terms, sales speed and loan terms.
  3. Build the outflows. Land cost, the Hard Cost S-curve according to payment terms, Soft Cost, marketing, commission and transfer day costs.
  4. Build the inflows. Booking deposits, progress instalments tied to construction progress, and transfer payments per the actual transfer schedule.
  5. Calculate net cash flow and the cumulative balance to find Peak Funding before financing.
  6. Add a funding-source waterfall. Use equity first, then loans as they can be drawn. Any excess is the funding gap.
  7. Calculate interest on the opening balance. This avoids circular references and still gives figures that are easy to understand.
  8. Add checks every month, and only then run scenarios.

Core formulas

ItemMonthly formulas
Net Hard Cost progress paymentProgress × Hard Cost × (1 − Advance Recovery − Retention)
Payments to contractorNet progress payments spread according to the payment lag, plus advance and retention release
Booking deposit + contract depositSales added this month × sales value × booking deposit %
Instalment paymentsChange in (cumulative sales × cumulative progress) × sales value × instalment %
Transfer paymentsUnits awaiting transfer × transfer schedule
InterestOpening debt × interest rate ÷ 12
Funding GapShortfall after equity and loan facilities are fully used

Peak Funding = the largest negative cumulative net cash flow before financing

Example table for the tightest period

Example project: payment terms 20/15/65, equity THB 400 million, facility THB 450 million, interest 7% per year, figures in THB million

MonthInflowsOutflowsNetInterestCumulative before financingClosing debtCumulative gap
2417.042.1−25.12.6−863.2450.029.9
2516.721.4−4.72.6−867.9450.037.2
2617.814.53.32.6−864.6450.036.6
2718.315.52.82.6−861.8450.036.4
2820.919.01.92.6−859.9450.037.2
2917.121.8−4.72.6−864.6450.044.4
3015.518.1−2.62.6−867.2450.049.7
31455.236.2418.92.6−448.383.40.0
32380.126.9353.20.5−95.10.00.0
33270.918.3252.60.0157.50.00.0
34161.711.1150.60.0308.20.00.0

Outflows exclude interest. The cumulative gap rises or falls with net cash flow after interest. When transfers begin in month 31, inflows repay the gap first and then the bank debt. In practice, the order must follow the loan agreement. If the bank has the right to be repaid first, the party that funded the gap must wait until the bank debt is cleared.

Checks every table needs

  • Total cumulative Hard Cost equals the budget, and the work categories add up to 100%
  • Total sales inflows equal the sales value used in the model
  • Payment terms add up to 100%
  • Sources equal Uses every month
  • Debt does not exceed the facility and is never negative
  • Total equity does not exceed what shareholders have agreed, before it becomes a gap
  • Cumulative profit matches closing cash at the end of the project

Reconciliation of the example project

Revenue from sales2,100.0
Less: land(250.0)
Less: Hard Cost(1,000.0)
Less: Soft Cost and contingency(170.0)
Less: marketing(42.0)
Less: commission(63.0)
Less: Specific Business Tax (SBT) at 3.3%(69.3)
Less: transfer fee at 1%(21.0)
Profit before interest and tax484.7
Less: interest(35.6)
Profit before tax449.1
Less: corporate income tax (CIT) at 20%(89.8)
Net profit359.3

For simplicity, this example calculates tax on the whole profit before tax. In practice, the calculation must be adjusted for revenue recognition rules, expense conditions and the tax year.

What to do once you see a gap

OptionEffect on the gapTrade-off
Adjust payment termsBrings in more cash before transferMay affect sales speed or require discounts
Accelerate sales to reach the target by the time construction is completeIncreases cumulative instalments and units awaiting transferHigher marketing budget and discounts
Pay commission in instalments linked to transfer dayReduces outflows during constructionMust be agreed with the sales channels
Extend credit termsTemporarily reduces outflowsMay require a larger performance bond or a higher price
Increase equity or a shareholder loanCloses the gap directlyLowers shareholder returns or ties up more money
Extend the facility or add mezzanine financingCloses the gap directlyCost and security requirements
Split construction into phasesReduces the peak per phaseConstruction cost and programme may increase

How to keep using the table

Review it monthly. Replace assumptions with actual figures from work certificates and sales reports, report variances from plan line by line, and link the 13-week forecast for near-term cash to the monthly table.

Emergency funding sources, in orderUse when
Existing cash reservesShort-term deviations
Committed facilities not yet drawnExpected shortfalls in the short to medium term
Uncommitted facilitiesA supplementary option, but the bank is not obliged to provide it
Shareholder LoanA gap that must be closed quickly
Sell non-core assetsA large gap with time to prepare
Bridge LoanNeeds money urgently; high cost; short-term use
Emergency equity injectionWhen no other route can close the gap
  • Watch for Days Cash on Hand below 30 days, sales speed below 50% of plan, or a cost overrun above 10%
  • Run stress tests covering lower sales, higher costs and construction delays
  • Request a facility extension or negotiate with the bank before the month in which the gap will arise